SF permit office fails to pull permit for project

SF permit office fails to pull permit for project

SANTA FE (KRQE) – The office that handles building permits for the City of Santa Fe, failed to pull permits for its own construction project and it’s going to cost taxpayers extra.

A city spokeswoman says they were doing a simple remodel in the land use department, converting a conference room to offices, when they suddenly got a call from the state regulation and licensing department asking where their permits were.

The spokeswoman says it was all a big misunderstanding and the project is now suspended.

Because of the delay, permit costs and other issues the $17,000 project is now going to cost another $6,000.

As for the fact that this was the very office that handles building permits and often fines others for failing to get them a porter says that is a complete coincidence and the people in the office had nothing to do with the project or pulling the permits.

KRQE.com provides commenting to allow for constructive discussion on the stories we cover. In order to comment here, you acknowledge you have read and agreed to our Terms of Service. Users who violate these terms, including use of vulgar language or racial slurs, will be banned. Please be respectful of the opinions of others. If you see an inappropriate comment, please flag it for our moderators to review.